Sill plates

Today started out pretty gently. We took a load of trash to the dump, and had a hot breakfast at Stella's.


Back on the hill, the sky was gorgeous.


Siggy was pretty pooped from yesterday, but he found ways to cope.


Our main task today was to prepare sill plates. They needed to be drilled to drop over the hold-down threaded rods we installed earlier in the week. Then we drilles a second set of holes to locate the anchor bolts, using the wood plates as templates to drill the holes for the anchors into the concrete.


Here Siggy and Eliot are measuring holes in a sill plate:


...and now they're drilling them.


All the plates fit perfectly. Eliot's taking them off to store in shelter. Last year, a week in the sun seriously warped our sill plates (for Cabin v1.0), so this year they don't sleep outside until they're bolted down.


Tomorrow, we'll drill for the anchors, and work on building the pony walls inside the foundation.

Comments

  1. I'm thinking you all 3 would want to be napping after yesterday. Love how Siggy gets to help. Nice, E. Gorgeous backdrop!

    ReplyDelete

Post a Comment

Popular posts from this blog

Current events

Saturday   Dan rode up with Eliot and I; Christina brought David, JJ, Peter, and Hannah. Lunch was eleven people. Another dump run. David worked on the pantry for the shedlet. We had to install one panel of siding so the meter base would end up on top of it. Dan & Eliot preparing the meter base and panels for dry fitting. Meter base is mounted; fitting the conduit. Sunday Preparing and installing the service entrance conductors. A shout out to my friend Brett who spent a few hours on the phone talking electrian-shop this week! This panel/meter layout and conduit routing was Eliot's solution to our panel placement problem. Meter base installed and wired to panels! Panels bonded & grounded to Ufer ground. An Ufer ground is basically rebar near the bottom of the concrete foundation that's continuous up through an access stub where it can be wired to the panel. Remarkably, the moisture in the concr...

A really big hole

The excavation team came today.  Paul, the excavator driver, helped Siggy scoop and dump the bucket. Then he taught Eliot how to drive and set him loose: The crew did get the foundation hole dug: Meanwhile, much of the family got a good start on painting the shop:

Getting going on electrical

Today we met with an electrician for advice, and then installed our temporary service pole and our meter and panel for the shop: We also pounded in the indoor receptacles, and covered the attic vents with critter resistant mesh. We also passed our foundation wall inspection. And we took a load of construction debris to the dump. Also I think we saw a bear. Update. It was probably this particular bear. Our neighbors snapped this photo the next day, writing "Hello all, we just had a young visitor-a yearling cinnamon black bear."