Skip to main content

Standing up the first walls

Another milestone today: we stood up one of the walls (in two sections).


We began with two sections, built flat on the floor. We moved them around with castered dollies.


Normally you can just tip a wall into place, but we have to lift ours up six inches and lower them down over the threaded hold-down rods. The short sections of wall shown above (each 13 feet long) weigh ... a lot. We built these "sippy bird" jacks to be able to lower the wall sections slowly.


First, we set the bottom edge of the wall up on 6" blocks. Then we tilt the wall to vertical (using brute force). Then we tack in a diagonal brace so it doesn't fall over on us. Then we attach a sippy-bird jack at each end. We lift one end, replace the 6" block with a 4-1/2" block, and lower it back down, guiding it over the threaded rods. We alternate sides until the wall is in place on the floor, then whack it with a sledgehammer until it's in the right place.

 Wildlife break. Our black grasshoppers turn bright yellow when they're flying.


Here are a couple of the hold-down brackets successfully installed over their threaded rods.


Eliot is aligning the two wall segment before we nail them together to become a single wall.


The completed wall is in the background. In the foreground, Eliot is nailing sheathing onto the next section of wall that we'll put up next weekend.


Comments

  1. Awesome progress Howell family!!!

    ReplyDelete
    Replies
    1. Awesome! Had no idea how big, or how far you had made it. Hopefully ian and I can come help out a little.

      Delete

Post a Comment

Popular posts from this blog

Current events

Saturday   Dan rode up with Eliot and I; Christina brought David, JJ, Peter, and Hannah. Lunch was eleven people. Another dump run. David worked on the pantry for the shedlet. We had to install one panel of siding so the meter base would end up on top of it. Dan & Eliot preparing the meter base and panels for dry fitting. Meter base is mounted; fitting the conduit. Sunday Preparing and installing the service entrance conductors. A shout out to my friend Brett who spent a few hours on the phone talking electrian-shop this week! This panel/meter layout and conduit routing was Eliot's solution to our panel placement problem. Meter base installed and wired to panels! Panels bonded & grounded to Ufer ground. An Ufer ground is basically rebar near the bottom of the concrete foundation that's continuous up through an access stub where it can be wired to the panel. Remarkably, the moisture in the concr...

A really big hole

The excavation team came today.  Paul, the excavator driver, helped Siggy scoop and dump the bucket. Then he taught Eliot how to drive and set him loose: The crew did get the foundation hole dug: Meanwhile, much of the family got a good start on painting the shop:

Getting going on electrical

Today we met with an electrician for advice, and then installed our temporary service pole and our meter and panel for the shop: We also pounded in the indoor receptacles, and covered the attic vents with critter resistant mesh. We also passed our foundation wall inspection. And we took a load of construction debris to the dump. Also I think we saw a bear. Update. It was probably this particular bear. Our neighbors snapped this photo the next day, writing "Hello all, we just had a young visitor-a yearling cinnamon black bear."