Siding Chapter III

 Friday

Drove the lift in and stopped at the bottom of the hill to take this glamour shot.



We installed the second level window head casing on the north wall.


Detailing in the plumbing vent.


Time to take out the trash.


Saturday


Guinivere and Eliot finished up some detailing on the east wall.



My mom came up; niece Bri went for a swing. Bri brought her dog Mozy.


Second layer, east wall. These were all single-cut rectangles; no windows or other details. Hooray!

Sunday



It didn't take long to wrap up the east wall.


We took a lunchtime break to shoot some senior portraits.


...and then back into grubby clothes to work on the third row of siding for the north wall.


We're still missing a few details at the top of the north wall, plus the panels where the front door will go, and the panel on the corner that will get installed after the temporary ground wire is removed. But besides those omissions, that's three walls with siding!

Next weekend: the big window wall on the south side.

Comments

Post a Comment

Popular posts from this blog

Current events

Saturday   Dan rode up with Eliot and I; Christina brought David, JJ, Peter, and Hannah. Lunch was eleven people. Another dump run. David worked on the pantry for the shedlet. We had to install one panel of siding so the meter base would end up on top of it. Dan & Eliot preparing the meter base and panels for dry fitting. Meter base is mounted; fitting the conduit. Sunday Preparing and installing the service entrance conductors. A shout out to my friend Brett who spent a few hours on the phone talking electrian-shop this week! This panel/meter layout and conduit routing was Eliot's solution to our panel placement problem. Meter base installed and wired to panels! Panels bonded & grounded to Ufer ground. An Ufer ground is basically rebar near the bottom of the concrete foundation that's continuous up through an access stub where it can be wired to the panel. Remarkably, the moisture in the concr...

A really big hole

The excavation team came today.  Paul, the excavator driver, helped Siggy scoop and dump the bucket. Then he taught Eliot how to drive and set him loose: The crew did get the foundation hole dug: Meanwhile, much of the family got a good start on painting the shop:

Getting going on electrical

Today we met with an electrician for advice, and then installed our temporary service pole and our meter and panel for the shop: We also pounded in the indoor receptacles, and covered the attic vents with critter resistant mesh. We also passed our foundation wall inspection. And we took a load of construction debris to the dump. Also I think we saw a bear. Update. It was probably this particular bear. Our neighbors snapped this photo the next day, writing "Hello all, we just had a young visitor-a yearling cinnamon black bear."