Eliot and I replaced our plywood front door with a cheap interior door from home depot, in an attempt to reduce the number of new mouse-shaped occupants.


We got the range wiring installed.

Next, we went after wiring the furnace. The good news was that we needed only a single run of 6awg wire -- we only needed a modest electric backup heater. The bad news was that the HVAC folks installed the furnace so that the electric supply input was 1.5" from a triple stud that we're not allowed to drill. We gave up at dinnertime.

Saturday


Eliot and Christina installed window trim legs on the laundry room window.


Siobhan and Eliot installed more legs on the kitchen windows. A little caulking got astray.


Siobhan shot a few bullseyes.


This is Isaac and Jennifer, the couple that designed the building last year. Eliot thought this looked like a stock photo architect meeting, so I made Isaac wear a hardhat.

Christina and Jon made the last few windowsills, and she painted them with Siggy. Here she's helping Eliot install the sill under the stairwell windows.

Christina and Jon also got the door center trim piece finished up and installed, which completes the trim on the front wall. Pretty gorgeous!

Siobhan and Jon touched up some sill ends that were missing primer. By the end of Saturday, we had all the window trim installed except for one window that still needs a piece of siding below. (It's waiting because the temporary electrical ground pops out of the wall right there.)

Sunday



Big winds Friday knocked a tree down on the dirt road we share with the neighbors. We used it as an excuse to cycle fresh fuel into our generators, so we chopped it up with electric chainsaws. We were just getting down to it when our neighbor showed up with his tractor to push the tree out of the way.

Eliot and Jon got back down into the crawlspace to finish the battle we began with the furnace; we emerged victorious.


A couple weeks ago we were cooling the shedlet with a fan. Next weekend, the overnight low is 25F/-4C. So we blew out the water line and hiked all the water-based paints and glues up to the shedlet where a heater keeps things above freezing.


Christina, Siggy, and Jon spent an hour taking dead limbs off trees in the woods with machetes and chainsaws.



Guinivere took these pictures in the woods.


The drive back to Yakima featured brilliant contrasts and vivid rainbows.

Comments

  1. The front view is awesome.
    Glad you got the water heater electrical solved.
    How would Siobhan rate her hair control product?

    ReplyDelete

Post a Comment

Popular posts from this blog

It is DONE!

The final inspection was today. This guy is Levi, the county inspector, and as you can see, we passed! He only had two questions for me. One was about the energy efficiency credits and the blower door test, for which I had the compensating paperwork for the low-flow faucets already prepared. The second was asking for a smoke detector outside the bedroom; I pointed up and he saw that we already had one tucked into the alcove. And that was that! I got up at 5am to be certain I'd be here before the inspector, and I was ... by about five hours. In that time, I took another truckload of tool buckets down to the storage container, then picked up all the floor protection in the great room and vacuumed and mopped. It's glowing! Then I went back down to the storage container to get a hammer so I could glue in 32 wood plugs to cover the screws for the french doors. I fought with installing the screens, but the frames are too big! The manufacturer said "yeah we don't even make th...

Odds and ends

I made progress on a bunch of little things today.  I painted a fencepost in 12" segments and pounded it in at the property line, where the outdoor camera can see it. Now we can measure the snow accumulation. I worked on finishing up almost-complete receptacle branch circuits. The first one I worked on was a little mystery: all the receptacles were installed, but the power didn't reach past a certain point in the line. After some investigation with a wire tracer and watching through the videos we took before covering the walls, I worked out what had happened: two receptacles shared a stud bay, facing into opposite rooms. The plan had been to bring power up to one box, jump over to the other box, and continue back down to the crawlspace to the next box. We forgot the jumper. I couldn't fish a wire between the boxes myself, so that repair waits. Upstairs, installing two receptacles completed the branch. The bathroom vent hole in the tile backer board was a skosh too small. ...

Energy efficiency testing

I came up after work to meet Brian, the contractor who is doing our blower door test: In this test, a big fan pumps air out of the house at a prescribed pressure differential, and then the air flow rate is measured in cubic feet per minute, then converted to whole house air changes per hour. The maximum limit is 5.0, and we scored that. Hooray! Brian said that we'd done a pretty solid job sealing the house, especially for an owner-built house; getting extremely tight seals requires careful awareness of the sealing challenges at every stage of construction. Another thing I learned by building a house. While I was up there, I got most of the way through installing a heat pump water heater to comply with energy efficiency requirements I re-discovered when looking up the blower door test requirements. This is all a bit silly. For our application -- a house occupied infrequently -- the on-demand heater is the best efficiency tradeoff, because it has zero standby waste. Unfortunately, th...