The first order of business for Jon's visit today was getting the internet working at the big cabin. The first subtask was removing this wasp nest inside the hole that the starlink cable comes through...


Then plugging the hole with a little 3D printed plug:


Then I routed some ethernet cord on the outside of the little cabin to a wifi extender. The other end of the extender is on the back side of the big cabin, with ethernet routed through the crawlspace to an access point under the stairs.

How did it take all day to run a couple ethernet cables!? Partly it was because I glanced at the conductor order guide and forgot it contained a subtle trap:
...I haven't crimped an ethernet connector in a very long time, apparently.


That left me a couple hours to make a little tiny bit more progress on the back deck. I added two rim boards to complete the rim joist.



Comments

Popular posts from this blog

Current events

Saturday   Dan rode up with Eliot and I; Christina brought David, JJ, Peter, and Hannah. Lunch was eleven people. Another dump run. David worked on the pantry for the shedlet. We had to install one panel of siding so the meter base would end up on top of it. Dan & Eliot preparing the meter base and panels for dry fitting. Meter base is mounted; fitting the conduit. Sunday Preparing and installing the service entrance conductors. A shout out to my friend Brett who spent a few hours on the phone talking electrian-shop this week! This panel/meter layout and conduit routing was Eliot's solution to our panel placement problem. Meter base installed and wired to panels! Panels bonded & grounded to Ufer ground. An Ufer ground is basically rebar near the bottom of the concrete foundation that's continuous up through an access stub where it can be wired to the panel. Remarkably, the moisture in the concr...

A really big hole

The excavation team came today.  Paul, the excavator driver, helped Siggy scoop and dump the bucket. Then he taught Eliot how to drive and set him loose: The crew did get the foundation hole dug: Meanwhile, much of the family got a good start on painting the shop:

Getting going on electrical

Today we met with an electrician for advice, and then installed our temporary service pole and our meter and panel for the shop: We also pounded in the indoor receptacles, and covered the attic vents with critter resistant mesh. We also passed our foundation wall inspection. And we took a load of construction debris to the dump. Also I think we saw a bear. Update. It was probably this particular bear. Our neighbors snapped this photo the next day, writing "Hello all, we just had a young visitor-a yearling cinnamon black bear."