Dried in! Window framing. Chimney.

So the really big news is from last Friday: the framers completed the plywoodr sheeting, and the roofer came up and got the 'ice & snow' synthetic roof felt down over it.

This is exciting: the roofers will be back in a week or two with metal, but it'll be raining by then. Because the wood is protected, they can go ahead with the metal anyway. Yay!

Monday

The framers continued on to frame out the fancy triangle windows in the front. Wow, it looks good!



You had to be there Monday. By Tuesday it was all covered up with plywood, in preparation for housewrap, which protects the sides of the structure from water through the winter -- or however long until we install windows and siding.

Tuesday

I came up tonight to sleep here for a plumber meeting in Ellensburg tomorrow morning. I used the visit to do a few errands: put diesel in the forklift, move some tools down to the house, and fix up one erroneous hold-down strap before the tyvek covers it.

Then I got down to business preparing the chimney and its support box that has to get fastened into the roof before the roofers add metal.




Nice.

Comments

Post a Comment

Popular posts from this blog

The trim finishing journey begins

The last time we installed wood trim (almost two years ago!), we sanded and cut the material inside the cabin (it was winter) and installed it unfinished. Finishing it meant taping everything off and applying three coats of finish in place. Removing the masking was frustrating (the finish glued it to the wall in places), and in other places the finish still got where it didn't belong. Now the cabin is full of nice, finished floors, cabinets, and counters. It's not a shop. So this time, I'm sanding and pre-finishing all the boards outdoors. Thankfully, there's still pretty nice weather; that black tarp garage heats up pretty well when the sun's out. Today I got the first batch of wood sanded and a coat of finish applied. Christina installed eight receptacles in the kitchen and great room. My mom came up to enjoy the warm ambiance of the not-yet-active wood stove.

Uncrating the wood stove

  I drove up to the cabin today to meet a tree contractor. Since I was up there anyway, I took care of some other business. I got the wood stove out and ready to install on Monday. I vacuumed up the tiny particles of styrofoam packaging material from last year's roofing panels that would have been much easier to clean up last year. I put the bathroom outlet back into its adjusted place above the backsplash. I corrected my installation of the heat pump wiring with a pair of reducing washers. Now it's really done. I replaced the emergency brake battery system in the flatbed trailer.  I bucked a bunch of old logs into rounds for firewood.

Odds and ends

I made progress on a bunch of little things today.  I painted a fencepost in 12" segments and pounded it in at the property line, where the outdoor camera can see it. Now we can measure the snow accumulation. I worked on finishing up almost-complete receptacle branch circuits. The first one I worked on was a little mystery: all the receptacles were installed, but the power didn't reach past a certain point in the line. After some investigation with a wire tracer and watching through the videos we took before covering the walls, I worked out what had happened: two receptacles shared a stud bay, facing into opposite rooms. The plan had been to bring power up to one box, jump over to the other box, and continue back down to the crawlspace to the next box. We forgot the jumper. I couldn't fish a wire between the boxes myself, so that repair waits. Upstairs, installing two receptacles completed the branch. The bathroom vent hole in the tile backer board was a skosh too small. ...