Monday
We added a couple of weekdays to make up for missing a weekend back when it was 108°F.
Christina varnished the exterior of the door.
Jon installed this modest little box, ready to deliver power to a water reservoir pump. It's the last branch circuit.
Jon installed junction boxes for accent lighting up by the collar ties, twenty feet over the kitchen.
Dinner was at Red Arrow Burgers.
Tuesday
Christina worked on the door finish.
Siggy found these monster dandelions.

Jon's drill bit found this piece of Romex. Thankfully it was an easy replacement.
Jon finished the accent lighting junction boxes.
We went around and looked for quality control issues. Too many cables were crammed into this wall. Christina pulled the staples out with sheer force of will.
Siggy installed blocking.
Christina stapled the cables down to the blocking.
Siobhan moved some line-voltage cables away from the thermostat wire.
Siggy rode the elevator.

Christina rearranged a cable in the panel that wasn't adequately clamped.